Planning and Projects
Tactical Plans for FY2009 - FY2011
January 2009
In Support of Enterprise Information System Infrastructure (IT)
- FY09: Banner hardware upgrades (complete)
- FY10: Banner software upgrade (to Banner 8)
- FY10/11: support for upgrades to unit-based Banner-edge applications
- FY11: possible conversion of Banner base system from OpenVMS to Unix/Linux
- FY09/10/11: continuing realization of effective Identity Management in Central Directory systems and features
- FY09/10/11: continuing efforts to make Central Directory software and hardware more robust
- FY09/10/11: continuing evolution of Central Directory schema
- FY09/10/11: continuing integration of applications with Central Directory authentication and authorization framework (e.g., "CASification")
- FY10/11: extension of UM-M identity management framework to other UM campuses and national federated identity frameworks
In Support of Networking Infrastructure (IT)
- FY09/10/11: continuing upgrades of in-building networks, building/core connections, campus core network, and campus edge capabilities
- FY09/10: upgrading metro-Missoula and regional connections
- FY09/10: implementation of new campus/campus connections based on new State network
- FY09/10: implementation of new campus connections through Northern Tier infrastructure
In Support of Electronic Application System Infrastructure (IT and units)
- FY09/10/11: continuing evolution of telephone system capabilities and administrative structure
- FY09: implementation of new UM-M home Web site
- FY09/10/11: continuing support for existing critical Web-services (e.g., OneStop)
- FY10/11: [limited by funding] continuing enhancement of UM-M home Web site
- FY10/11: [limited by funding] development of additional Web-based services
- FY09: implementation of Web content management system (CMS)
- FY09/10/11: continuing support for utilization of the CMS in unit Web sites and content
- FY09: outsourcing of student email to Microsoft
- FY10/11: continuing evolution of student email and other services on the Microsoft platform
- FY10/11: [limited by funding] evolution of faculty/staff email (i.e., reduced to a 2,000 user system vs. the current 20,000 user system), including effective email archiving/retrieval
- FY09: introduction of more effective email communication mechanisms
- FY10/11: [limited by funding] introduction and promotion of "closed system" communications as an alternative to (open to the world, with attendant problems) email communications
- FY09: implement of (limited) hosting space for unit-operated servers (LA basement)
- FY10/11: [pending funding] development of plan and implementation of plan for expanded/enhanced hosting space for IT and unit-operated servers
In Support of Classroom/Instructional Technology Support Infrastructure (IT with AA)
- FY09: development of plan for classroom technology enhancement
- FY10/11: [just complete?] implementation of classroom technology enhancement plan
- FY09: development of plan for learning management system (LMS) evolution
- FY10/11: [pending funding] implementation of LMS evolution plan
- FY09: development of plan for enhancing faculty instructional technology support
- FY10/11: [pending funding] implementation of faculty instructional technology support plan